Development of the Quality Enhancement Plan

Criterion 2.12, the QEP

Selected Current Quality Enhancement Projects

Activity Scheduled
Completion
Actual
Completion
Define the project (intervention and measurement)September 30
Leadership team
QEP committee chairs
Research committee
Data Collection committee
Activities:
Review other QEPsSeptember 15
Identify specific learning outcomes and measurements
Collect initial bibliographic information
Develop detailed outline of plan
Deliverable: Project definition document
 
Development of planMarch 31, 2008
Leadership team
Research committee
Writing committee
QEP committee chairs
Activities:
Literature search
Refine definition of measurements
Write draft plan
Deliverable: Draft plan
 
Baseline data collectionMay 31, 2008
Data collection committee
Activities:
Collection of baseline data from retrospective information if appropriate
Establish mechanism for collection of baseline data going forward
Begin collection of data
Deliverable: Baseline data
 
Final planDecember 31, 2008
Leadership team
QEP committee chairs
Data collection committee
Writing committee
Activities:
Continue baseline data collection
Revise plan as required
Deliverable: Final plan
 
Plan approvalJanuary 15, 2009
Leadership team
Deliverable: Approved plan
 
Delivery of plan to SACSFebruary 7, 2009
QEP chair